The Robinvale Solar Farm Project provided an excellent opportunity for our team to deploy our first PVH duo tracking system. The piling commenced January 2020 in Robinvale, Victoria. The 9.4 MWDC / 7.4 MWAC solar farm can be found on Pethard Road, approximately 500km NW of Melbourne on Australia’s southeast coast.
3980 piles were installed in 2 weeks with 4 x Pile driving rigs and Pilecom accomplished the extremely tight tolerance needed for this tracking system.
Equipment Used
- 4 x Orteco HD1500 – Pile driver
PROJECT STATS